Industrial Cladding Transformation in Leeds

Project Overview

CJ Paint Spraying was appointed to restore and rejuvenate the external appearance of a large industrial building in Leeds. The existing asbestos-cement wall cladding had become weathered over time and required specialist refurbishment to improve its appearance while retaining the existing sheets.

Due to the nature of the asbestos-cement cladding, the project required a carefully controlled approach to cleaning, preparation and coating. Rather than removing or unnecessarily disturbing the existing material, the works were designed to safely refurbish the cladding in situ and provide a durable, consistent new finish across the treated elevations.

The refurbishment covered both the road-facing and canal-facing elevations of the building. The lower stone walls were also professionally cleaned as part of the works but were intentionally left unpainted, retaining their existing appearance. The project was focused entirely on the external wall elevations, with roof works specifically excluded from the scope.

Project Details

RAL 5008Sector:
Commercial

Project:
External industrial cladding refurbishment. Asbestos-cement wall cladding

Scope:
A complete external refurbishment of an industrial building, delivered safely despite challenging access from both a public highway and a canal.

Location: Leeds

Programme: Two Weeks

Coating System: GUARD ELC

Colour: RAL 5008

Access: 16-metre articulated boom and 25.6-metre long-reach boom

 

The Challenge

Access was the most demanding aspect of this project for the Cj Paint Spraying team. One side of the industrial building faced a public road, while the opposite elevation ran alongside a canal. These very different surroundings meant that conventional access arrangements were not suitable and a separate, carefully planned approach was required for each elevation.

For the road-facing elevations, access was provided using a 16-metre articulated boom. An authorised partial lane closure was put in place to create a controlled working area, allowing the team to safely reach and complete the required sections of cladding while managing the restrictions presented by the adjacent public road.

The canal-facing elevation presented a different access challenge. To reach the cladding safely, CJ Paint Spraying used a 25.6-metre long-reach boom, positioned from a specially assessed location. Before work commenced, the machine's working radius, ground conditions and available operating area were all carefully reviewed to ensure the access equipment could be positioned and operated safely throughout the works.

Our Approach

The refurbishment was carried out in carefully controlled stages, with the preparation and coating process designed to improve and protect the existing asbestos-cement cladding while avoiding unnecessary disturbance to the sheets.

The cladding was first gently cleaned using plain water to remove surface dirt and contamination. Once clean, the existing sheets, fixings, laps and other vulnerable areas were inspected and prepared using non-invasive methods appropriate for the asbestos-cement substrate. Adjacent surfaces and any areas not included within the coating works were fully masked and protected before spraying commenced.

A water-based GUARD ELC protective coating was then applied to the prepared cladding in RAL 5008, providing a durable and consistent new finish across the treated elevations. The lower stonework was separately jet washed to restore its appearance but deliberately retained in its natural, unpainted finish. Each elevation was inspected as the work progressed to maintain a consistent standard of finish throughout the project.

The chosen refurbishment method allowed the existing asbestos-cement cladding to remain in place, avoiding the additional disruption that would have been involved in removing and replacing the sheets.

Safe Delivery

Due to the combination of asbestos-cement cladding and the building's challenging position between a public road and canal, the entire project was completed under detailed site-specific RAMS. Safety and access arrangements formed an important part of the programme from the outset.

All MEWP operations were carried out by IPAF-trained operators, supported by a dedicated banksman and trained ground rescuer. Plant and access equipment were inspected daily, while dedicated traffic, pedestrian and canal-side exclusion zones were established to maintain a controlled working environment.

Working alongside and, where required, over the canal was carefully controlled, with appropriate pollution-prevention measures in place throughout. Non-invasive preparation methods were used on the asbestos-cement cladding, and at no point were operatives permitted to walk or stand on the roof or cladding sheets.

The programme was carefully managed around weather conditions, access restrictions and the coating manufacturer's application requirements, allowing each stage of the refurbishment to be completed safely and under the correct conditions.

See the Transformation

The Result

The completed refurbishment transformed the external appearance of the industrial building, replacing the tired and weathered finish with a clean, uniform RAL 5008 coating. Both the road-facing and canal-facing elevations were successfully restored, creating a consistent finish across the treated cladding while retaining the existing asbestos-cement sheets.

The lower stonework was professionally cleaned and left in its natural, unpainted finish, providing an attractive contrast against the newly coated cladding and helping to refresh the overall appearance of the property.

Despite the challenging access requirements presented by the public road and canal-side elevations, the project was completed safely and professionally in approximately two weeks, with disruption to the surrounding area kept to a minimum.

The finished project demonstrates how specialist access planning, controlled preparation and a high-performance coating system can be combined to successfully refurbish existing industrial cladding, even where the location and surrounding environment present particularly complex access challenges.