CJ Paint Spraying developed a specialist refurbishment package for an industrial asbestos-cement roof in Heysham, Lancashire, combining protective coating works with detailed preparation and site-specific access planning.

The project specified a two-coat RD Elastodeck system, with a target total dry film thickness of 300 microns and a light grey finish. Careful consideration was given to the practical requirements of working on an existing asbestos-cement roof, including protected access routes, material lifting arrangements and the collection of cleaning runoff.

By combining a clearly defined coating specification with detailed method planning and quality control requirements, the proposed works provided a structured approach to refurbishing the existing industrial roof covering.

Project Details

Service:
Asbestos-Cement Roof Coating & Refurbishment

Scope:
Roof preparation, protective coating specification, access planning and runoff management

Location: Heysham, Lancashire

 

 

The Project Challenge

Refurbishing an existing asbestos-cement roof requires more than selecting a suitable protective coating. The preparation methods, access arrangements and handling of cleaning materials all need to be considered carefully before work begins.

At the Heysham industrial property, one of the main challenges was establishing a safe and practical method of accessing the roof while protecting the existing asbestos-cement sheets. The proposed works required designated access routes and suitable arrangements for lifting materials and equipment into position.
Surface preparation also presented important considerations. Moss, debris and sediment needed to be accounted for, alongside the collection and containment of liquid runoff generated during the preparation process.

The coating specification introduced further technical requirements. The proposed two-coat RD Elastodeck system needed to achieve a total dry film thickness of 300 microns, supported by appropriate application checks and records.

The challenge was therefore to bring together the coating requirements, preparation methods and site logistics into a coordinated refurbishment plan that could be reviewed before mobilisation.

Our Approach

CJ Paint Spraying developed a structured approach to the proposed roof refurbishment, focusing on the technical coating specification and the practical arrangements needed to undertake the works.

The refurbishment package identified the required coating system, target film thickness and supporting quality control procedures. Alongside this, the site method considered roof access, material handling and the collection of runoff from preparation activities.

These elements were reviewed together to ensure the proposed coating works could be assessed against the specific conditions of the industrial property.

Roof Preparation and Access Planning

Careful planning was undertaken to establish suitable working arrangements across the existing asbestos-cement roof.

The proposed method included protected access routes to support movement around the roof, together with lifting arrangements for transporting materials and equipment to the work areas.

Preparation planning also addressed the removal and handling of moss, debris and sediment from the roof surface.

Particular attention was given to the collection of liquid runoff, including the containment capacity required during preparation activities.

These arrangements formed an important part of the method statements reviewed by the site team before the proposed works could proceed.

Protective Roof Coating Specification

The refurbishment package specified RD Elastodeck, a protective coating system selected for the existing industrial roof.

The proposed application consisted of two coats, with a combined dry film thickness target of 300 microns.

A light grey finish was selected as the preferred colour direction, although the exact colour reference was to be confirmed separately.

The specification established measurable coating requirements rather than relying solely on the finished appearance of the roof.

This provided a technical basis for assessing the proposed treatment and reviewing the application against the agreed requirements.

Application Monitoring and Quality Control

Quality control requirements were incorporated into the coating specification to support consistent application and traceability.

The proposed monitoring process included wet film thickness measurements, product batch information, coating coverage records and weather conditions during application.

These records were intended to provide supporting information for reviewing the coating process against the specified two-coat system and overall film thickness target.

By establishing these requirements in advance, the project provided a framework for documenting the application and assessing the completed treatment through final inspection and recorded results.

Coordination and Site Considerations

An important aspect of the Heysham project was ensuring that the proposed coating system could be delivered within the practical constraints of the industrial site.

The planning process considered how operatives and materials would access the roof, how preparation activities would be managed and what arrangements would be required to collect runoff.

The site team reviewed the proposed method statements, allowing the access and preparation procedures to be assessed before mobilisation.

This coordination helped establish a clearer understanding of both the technical coating requirements and the practical arrangements associated with the refurbishment.

For an industrial property, this approach provides a more complete basis for evaluating roof refurbishment works, considering not only the intended protective finish but also the methods required to prepare and treat the existing covering.

See the Transformation

The Result

The Heysham project established a detailed refurbishment package for the existing industrial asbestos-cement roof, combining a defined protective coating system with the practical arrangements needed for preparation and application.

The specified two-coat RD Elastodeck system, with a target total dry film thickness of 300 microns, provided clear technical requirements against which the proposed application could be assessed.
Alongside the coating specification, the planning addressed protected roof access, material handling, runoff containment and the management of debris generated during preparation.

The resulting package demonstrates CJ Paint Spraying's approach to specialist industrial asbestos-cement roof refurbishment, bringing together technical coating knowledge, practical site planning and quality assurance requirements to support a carefully managed refurbishment programme.

Final application records and inspection findings would be required to confirm the completed coating treatment against the specification.